Migrating to Sybase Adaptive Server Enterprise 11.5 D-13
Adaptive Server Enterprise 11.5 Cutover Migration Task List Example
Cutover Migration Task List Example
This sample task list covers a cutover migration approach to upgrade
SQL Server 10.x to Adaptive Server 11.5. The scenario for this task list
is:
The mid-sized company requires a simple, somewhat fault-
tolerant upgrade.
In the event of failure, the company depends on nightly backups.
The system cannot be down more than one hour and cannot
afford more than eight hours of data loss.
The environment includes development, test, and production
systems.
This example does not repeat the preparation steps given in previous
examples.
Set Up Adaptive Server 11.5 Environment on Development System
1. Configure the physical drives and local array, duplicate the
environment of the Release 10.x development system.
2. Perform a dump of the Release 10.x development system.
3. Install Adaptive Server 11.5.
4. Configure Adaptive Server 11.5 on the development system,
duplicating the Release 10.x development environment.
5. Update the interfaces file.
6. Create the databases on Adaptive Server 11.5.
7. Load the dump of the Release 10.x development system.
8. Run
dbcc commands (checktable, checkalloc, checkcatalog) on Adaptive
Server 11.5 databases. Be sure to verify the
dbcc log and error log.
9. Synchronize user IDs between the Release 10.x and 11.5
development systems.
10. Run
checkpoint on the Release 11.5 environment.
11. Shift development to Adaptive Server 11.5. Developers begin
verification and new feature development.